0 of 20 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
Information
- Questions: 20
You have already completed the Test before. Hence you can not start it again.
Test is loading...
You must sign in or sign up to start the Test.
You have to finish following quiz, to start this Test:
Your results are here!! for" CAIIB Paper 3 Module B Quiz 6 "
0 of 20 questions answered correctly
Your time:
Time has elapsed
Your Final Score is : 0
You have attempted : 0
Number of Correct Questions : 0 and scored 0
Number of Incorrect Questions : 0 and Negative marks 0
-
Not categorized
You have attempted: 0
Number of Correct Questions: 0 and scored 0
Number of Incorrect Questions: 0 and Negative marks 0
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- Answered
- Review
-
Question 1 of 20
1. Question
A project requires ₹5 lakh now and is expected to generate cash flows whose present value is ₹6.2 lakh. What is its NPV?
Correct
NPV = present value of inflows − initial outlay = ₹6.2 lakh − ₹5 lakh = ₹1.2 lakh. Positive NPV indicates expected value addition at the discount rate used.
Incorrect
NPV = present value of inflows − initial outlay = ₹6.2 lakh − ₹5 lakh = ₹1.2 lakh. Positive NPV indicates expected value addition at the discount rate used.
Unattempted
NPV = present value of inflows − initial outlay = ₹6.2 lakh − ₹5 lakh = ₹1.2 lakh. Positive NPV indicates expected value addition at the discount rate used.
-
Question 2 of 20
2. Question
A project’s IRR is 14% and its appropriate required return is 11%. For a conventional project, the IRR rule suggests:
Correct
For a conventional independent project, IRR above the required return generally indicates positive NPV. NPV remains the preferred criterion for mutually exclusive projects with unusual cash flows.
Incorrect
For a conventional independent project, IRR above the required return generally indicates positive NPV. NPV remains the preferred criterion for mutually exclusive projects with unusual cash flows.
Unattempted
For a conventional independent project, IRR above the required return generally indicates positive NPV. NPV remains the preferred criterion for mutually exclusive projects with unusual cash flows.
-
Question 3 of 20
3. Question
When mutually exclusive projects have unequal lives and are repeatable, a useful comparison approach may be:
Correct
Equivalent annual value converts NPV or cost into an annual equivalent and can help compare repeatable alternatives with unequal lives. The method relies on appropriate repeatability and other assumptions.
Incorrect
Equivalent annual value converts NPV or cost into an annual equivalent and can help compare repeatable alternatives with unequal lives. The method relies on appropriate repeatability and other assumptions.
Unattempted
Equivalent annual value converts NPV or cost into an annual equivalent and can help compare repeatable alternatives with unequal lives. The method relies on appropriate repeatability and other assumptions.
-
Question 4 of 20
4. Question
When project cash flows include expected inflation, the discount rate should generally be:
Correct
Nominal cash flows should be discounted at a nominal rate, while real cash flows should be discounted at a real rate. Mixing nominal and real measures produces inconsistent valuations.
Incorrect
Nominal cash flows should be discounted at a nominal rate, while real cash flows should be discounted at a real rate. Mixing nominal and real measures produces inconsistent valuations.
Unattempted
Nominal cash flows should be discounted at a nominal rate, while real cash flows should be discounted at a real rate. Mixing nominal and real measures produces inconsistent valuations.
-
Question 5 of 20
5. Question
In project appraisal, disposal proceeds from an asset should be adjusted for:
Correct
Terminal disposal proceeds may create a taxable gain or deductible loss relative to tax written-down value, depending on the applicable tax rules. Selling costs and tax effects should be reflected in after-tax cash flow.
Incorrect
Terminal disposal proceeds may create a taxable gain or deductible loss relative to tax written-down value, depending on the applicable tax rules. Selling costs and tax effects should be reflected in after-tax cash flow.
Unattempted
Terminal disposal proceeds may create a taxable gain or deductible loss relative to tax written-down value, depending on the applicable tax rules. Selling costs and tax effects should be reflected in after-tax cash flow.
-
Question 6 of 20
6. Question
For a project with tax-deductible depreciation, a faster depreciation schedule may:
Correct
Faster tax depreciation may bring tax savings forward, increasing their present value. The result depends on tax law, taxable income and whether deductions can be used.
Incorrect
Faster tax depreciation may bring tax savings forward, increasing their present value. The result depends on tax law, taxable income and whether deductions can be used.
Unattempted
Faster tax depreciation may bring tax savings forward, increasing their present value. The result depends on tax law, taxable income and whether deductions can be used.
-
Question 7 of 20
7. Question
The economic life of an asset is the period over which:
Correct
Economic life reflects the period over which operating benefits justify ownership relative to replacement or other alternatives. It may differ from the accounting depreciation life.
Incorrect
Economic life reflects the period over which operating benefits justify ownership relative to replacement or other alternatives. It may differ from the accounting depreciation life.
Unattempted
Economic life reflects the period over which operating benefits justify ownership relative to replacement or other alternatives. It may differ from the accounting depreciation life.
-
Question 8 of 20
8. Question
A post-completion audit of a capital project is intended mainly to:
Correct
Post-audits compare actual performance with projections, identify forecast errors and implementation issues, and improve accountability and future capital-budgeting decisions.
Incorrect
Post-audits compare actual performance with projections, identify forecast errors and implementation issues, and improve accountability and future capital-budgeting decisions.
Unattempted
Post-audits compare actual performance with projections, identify forecast errors and implementation issues, and improve accountability and future capital-budgeting decisions.
-
Question 9 of 20
9. Question
For an overseas project, a sound appraisal should ordinarily:
Correct
Foreign-currency cash flows should be discounted using a rate consistent with that currency’s inflation and risk assumptions, or converted consistently into home currency. Exchange and country risks also require consideration.
Incorrect
Foreign-currency cash flows should be discounted using a rate consistent with that currency’s inflation and risk assumptions, or converted consistently into home currency. Exchange and country risks also require consideration.
Unattempted
Foreign-currency cash flows should be discounted using a rate consistent with that currency’s inflation and risk assumptions, or converted consistently into home currency. Exchange and country risks also require consideration.
-
Question 10 of 20
10. Question
An overseas subsidiary earns profits but faces restrictions on remitting dividends. The parent’s project appraisal should:
Correct
The parent’s value depends on cash flows it can actually receive. Remittance controls, taxes, blocked funds and timing can affect the amount and present value of cash available to the parent.
Incorrect
The parent’s value depends on cash flows it can actually receive. Remittance controls, taxes, blocked funds and timing can affect the amount and present value of cash available to the parent.
Unattempted
The parent’s value depends on cash flows it can actually receive. Remittance controls, taxes, blocked funds and timing can affect the amount and present value of cash available to the parent.
-
Question 11 of 20
11. Question
A project’s local currency is expected to depreciate sharply. This may affect the project through:
Correct
Currency movements can alter the home-currency value of operating cash flows, assets, liabilities and remittances. The net effect depends on the currency of revenues, costs, debt and restrictions.
Incorrect
Currency movements can alter the home-currency value of operating cash flows, assets, liabilities and remittances. The net effect depends on the currency of revenues, costs, debt and restrictions.
Unattempted
Currency movements can alter the home-currency value of operating cash flows, assets, liabilities and remittances. The net effect depends on the currency of revenues, costs, debt and restrictions.
-
Question 12 of 20
12. Question
International portfolio investment differs from foreign direct investment mainly because portfolio investment typically:
Correct
Portfolio investment generally involves financial assets such as shares and bonds without the same intent to exercise lasting management control characteristic of FDI. Regulatory definitions and thresholds can vary.
Incorrect
Portfolio investment generally involves financial assets such as shares and bonds without the same intent to exercise lasting management control characteristic of FDI. Regulatory definitions and thresholds can vary.
Unattempted
Portfolio investment generally involves financial assets such as shares and bonds without the same intent to exercise lasting management control characteristic of FDI. Regulatory definitions and thresholds can vary.
-
Question 13 of 20
13. Question
If the risk-free rate is 5%, market risk premium is 7% and beta is 0.8, CAPM required return is:
Correct
CAPM required return = Rf + β × market risk premium = 5% + 0.8 × 7% = 10.6%.
Incorrect
CAPM required return = Rf + β × market risk premium = 5% + 0.8 × 7% = 10.6%.
Unattempted
CAPM required return = Rf + β × market risk premium = 5% + 0.8 × 7% = 10.6%.
-
Question 14 of 20
14. Question
An analyst adds a defensible country-risk premium to a project discount rate. The purpose is to:
Correct
A country-risk premium can be used to reflect additional country-specific risk when appropriate. The analyst must ensure the risk is not already reflected in cash flows or another risk adjustment.
Incorrect
A country-risk premium can be used to reflect additional country-specific risk when appropriate. The analyst must ensure the risk is not already reflected in cash flows or another risk adjustment.
Unattempted
A country-risk premium can be used to reflect additional country-specific risk when appropriate. The analyst must ensure the risk is not already reflected in cash flows or another risk adjustment.
-
Question 15 of 20
15. Question
An Indian exporter expecting a fixed USD receipt in three months wants to reduce uncertainty in its INR proceeds. A common tool is:
Correct
A forward contract can lock an exchange rate for a future conversion, reducing uncertainty in the INR value of a known foreign-currency receipt. It also removes the opportunity to benefit from favourable rate movements.
Incorrect
A forward contract can lock an exchange rate for a future conversion, reducing uncertainty in the INR value of a known foreign-currency receipt. It also removes the opportunity to benefit from favourable rate movements.
Unattempted
A forward contract can lock an exchange rate for a future conversion, reducing uncertainty in the INR value of a known foreign-currency receipt. It also removes the opportunity to benefit from favourable rate movements.
-
Question 16 of 20
16. Question
When transfer prices shift reported profit between subsidiaries, project analysis should emphasise:
Correct
The group should focus on actual consolidated cash flows and comply with transfer-pricing rules. Internal prices can affect tax allocation and local incentives, but should not be treated as creating value by themselves.
Incorrect
The group should focus on actual consolidated cash flows and comply with transfer-pricing rules. Internal prices can affect tax allocation and local incentives, but should not be treated as creating value by themselves.
Unattempted
The group should focus on actual consolidated cash flows and comply with transfer-pricing rules. Internal prices can affect tax allocation and local incentives, but should not be treated as creating value by themselves.
-
Question 17 of 20
17. Question
A project has NPV ₹8 lakh in a strong-demand scenario (probability 0.25), ₹3 lakh in a base scenario (0.50), and −₹2 lakh in a weak scenario (0.25). Expected NPV is:
Correct
Expected NPV = 0.25×8 + 0.50×3 + 0.25×(−2) = 2 + 1.5 − 0.5 = ₹3 lakh.
Incorrect
Expected NPV = 0.25×8 + 0.50×3 + 0.25×(−2) = 2 + 1.5 − 0.5 = ₹3 lakh.
Unattempted
Expected NPV = 0.25×8 + 0.50×3 + 0.25×(−2) = 2 + 1.5 − 0.5 = ₹3 lakh.
-
Question 18 of 20
18. Question
Two projects have equal expected NPV, but one has a much greater probability of a severe loss. A decision-maker should:
Correct
Equal expected values do not imply equal risk. Decision-makers should assess downside outcomes, volatility, liquidity impact and risk appetite, especially where severe losses could threaten the firm.
Incorrect
Equal expected values do not imply equal risk. Decision-makers should assess downside outcomes, volatility, liquidity impact and risk appetite, especially where severe losses could threaten the firm.
Unattempted
Equal expected values do not imply equal risk. Decision-makers should assess downside outcomes, volatility, liquidity impact and risk appetite, especially where severe losses could threaten the firm.
-
Question 19 of 20
19. Question
The option to delay an irreversible project until more information arrives is an example of:
Correct
A real option is managerial flexibility embedded in a real investment, such as the ability to delay, expand, contract or abandon a project as uncertainty resolves. Conventional NPV may understate this flexibility.
Incorrect
A real option is managerial flexibility embedded in a real investment, such as the ability to delay, expand, contract or abandon a project as uncertainty resolves. Conventional NPV may understate this flexibility.
Unattempted
A real option is managerial flexibility embedded in a real investment, such as the ability to delay, expand, contract or abandon a project as uncertainty resolves. Conventional NPV may understate this flexibility.
-
Question 20 of 20
20. Question
A project can be sold for a meaningful salvage value if demand collapses. This flexibility is best described as:
Correct
An abandonment option allows management to stop the project and recover salvage value when continuation is unattractive. This can reduce downside risk and add value, subject to the cost and feasibility of exit.
Incorrect
An abandonment option allows management to stop the project and recover salvage value when continuation is unattractive. This can reduce downside risk and add value, subject to the cost and feasibility of exit.
Unattempted
An abandonment option allows management to stop the project and recover salvage value when continuation is unattractive. This can reduce downside risk and add value, subject to the cost and feasibility of exit.