Your results are here!! for" CAIIB Paper 3 Module B Quiz 4 "
0 of 20 questions answered correctly
Your time:
Time has elapsed
Your Final Score is : 0
You have attempted : 0
Number of Correct Questions : 0 and scored 0
Number of Incorrect Questions : 0 and Negative marks 0
-
Not categorized
You have attempted: 0
Number of Correct Questions: 0 and scored 0
Number of Incorrect Questions: 0 and Negative marks 0
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- Answered
- Review
-
Question 1 of 20
1. Question
Sensitivity analysis in capital budgeting generally examines:
Correct
Sensitivity analysis changes one variable at a time—such as sales volume, price or cost—to see how the project outcome responds. It identifies important drivers but does not directly show the probability of outcomes.
Incorrect
Sensitivity analysis changes one variable at a time—such as sales volume, price or cost—to see how the project outcome responds. It identifies important drivers but does not directly show the probability of outcomes.
Unattempted
Sensitivity analysis changes one variable at a time—such as sales volume, price or cost—to see how the project outcome responds. It identifies important drivers but does not directly show the probability of outcomes.
-
Question 2 of 20
2. Question
Scenario analysis differs from simple sensitivity analysis because it:
Correct
Scenario analysis evaluates internally consistent combinations of inputs, such as a recession case with lower volume and prices and higher costs. It shows the combined impact of several variables changing together.
Incorrect
Scenario analysis evaluates internally consistent combinations of inputs, such as a recession case with lower volume and prices and higher costs. It shows the combined impact of several variables changing together.
Unattempted
Scenario analysis evaluates internally consistent combinations of inputs, such as a recession case with lower volume and prices and higher costs. It shows the combined impact of several variables changing together.
-
Question 3 of 20
3. Question
Monte Carlo simulation is useful because it:
Correct
Simulation repeatedly draws values from specified probability distributions for uncertain inputs and calculates project outcomes. It can estimate an outcome distribution, but its usefulness depends on sound assumptions and modelling.
Incorrect
Simulation repeatedly draws values from specified probability distributions for uncertain inputs and calculates project outcomes. It can estimate an outcome distribution, but its usefulness depends on sound assumptions and modelling.
Unattempted
Simulation repeatedly draws values from specified probability distributions for uncertain inputs and calculates project outcomes. It can estimate an outcome distribution, but its usefulness depends on sound assumptions and modelling.
-
Question 4 of 20
4. Question
A decision tree is particularly useful when:
Correct
Decision trees map sequential decisions, uncertain events and their payoffs. They help compare strategies that can adapt as information arrives, using probabilities and appropriate discounting.
Incorrect
Decision trees map sequential decisions, uncertain events and their payoffs. They help compare strategies that can adapt as information arrives, using probabilities and appropriate discounting.
Unattempted
Decision trees map sequential decisions, uncertain events and their payoffs. They help compare strategies that can adapt as information arrives, using probabilities and appropriate discounting.
-
Question 5 of 20
5. Question
A project yields ₹10 lakh with probability 0.6 and a loss of ₹4 lakh with probability 0.4. Its expected monetary value is:
Correct
Expected monetary value = 0.6 × ₹10 lakh + 0.4 × (−₹4 lakh) = ₹6 lakh − ₹1.6 lakh = ₹4.4 lakh. This is a probability-weighted average, not a guaranteed result.
Incorrect
Expected monetary value = 0.6 × ₹10 lakh + 0.4 × (−₹4 lakh) = ₹6 lakh − ₹1.6 lakh = ₹4.4 lakh. This is a probability-weighted average, not a guaranteed result.
Unattempted
Expected monetary value = 0.6 × ₹10 lakh + 0.4 × (−₹4 lakh) = ₹6 lakh − ₹1.6 lakh = ₹4.4 lakh. This is a probability-weighted average, not a guaranteed result.
-
Question 6 of 20
6. Question
A project with greater systematic risk than the firm’s existing operations would normally require:
Correct
A higher-risk project generally requires a higher expected return, reflecting its risk. A risk-adjusted discount rate is one approach, though certainty-equivalent cash flows or other methods may be used.
Incorrect
A higher-risk project generally requires a higher expected return, reflecting its risk. A risk-adjusted discount rate is one approach, though certainty-equivalent cash flows or other methods may be used.
Unattempted
A higher-risk project generally requires a higher expected return, reflecting its risk. A risk-adjusted discount rate is one approach, though certainty-equivalent cash flows or other methods may be used.
-
Question 7 of 20
7. Question
The certainty-equivalent approach adjusts for risk by:
Correct
The certainty-equivalent method reduces risky expected cash flows to amounts considered equivalent to certain cash flows, then discounts them at the risk-free rate. Risk is reflected in the cash-flow adjustment rather than solely in the discount rate.
Incorrect
The certainty-equivalent method reduces risky expected cash flows to amounts considered equivalent to certain cash flows, then discounts them at the risk-free rate. Risk is reflected in the cash-flow adjustment rather than solely in the discount rate.
Unattempted
The certainty-equivalent method reduces risky expected cash flows to amounts considered equivalent to certain cash flows, then discounts them at the risk-free rate. Risk is reflected in the cash-flow adjustment rather than solely in the discount rate.
-
Question 8 of 20
8. Question
The Hillier approach in capital budgeting is associated with:
Correct
The Hillier model is a capital-budgeting risk approach that considers the variance of project cash flows and correlations among periods to assess the variability of project value.
Incorrect
The Hillier model is a capital-budgeting risk approach that considers the variance of project cash flows and correlations among periods to assess the variability of project value.
Unattempted
The Hillier model is a capital-budgeting risk approach that considers the variance of project cash flows and correlations among periods to assess the variability of project value.
-
Question 9 of 20
9. Question
Project A has expected NPV ₹10 lakh and standard deviation ₹2 lakh; Project B has expected NPV ₹20 lakh and standard deviation ₹6 lakh. Which has the lower coefficient of variation?
Correct
Coefficient of variation = standard deviation ÷ expected value. A: 2/10 = 0.20; B: 6/20 = 0.30. Project A has lower relative risk per unit of expected NPV under this measure.
Incorrect
Coefficient of variation = standard deviation ÷ expected value. A: 2/10 = 0.20; B: 6/20 = 0.30. Project A has lower relative risk per unit of expected NPV under this measure.
Unattempted
Coefficient of variation = standard deviation ÷ expected value. A: 2/10 = 0.20; B: 6/20 = 0.30. Project A has lower relative risk per unit of expected NPV under this measure.
-
Question 10 of 20
10. Question
Which type of risk is generally reduced by holding a diversified portfolio of investments?
Correct
Diversification can reduce firm-specific risk because adverse events affecting one asset may be offset by others. It cannot eliminate systematic risks that affect the broader market.
Incorrect
Diversification can reduce firm-specific risk because adverse events affecting one asset may be offset by others. It cannot eliminate systematic risks that affect the broader market.
Unattempted
Diversification can reduce firm-specific risk because adverse events affecting one asset may be offset by others. It cannot eliminate systematic risks that affect the broader market.
-
Question 11 of 20
11. Question
Using CAPM, risk-free rate is 6%, beta is 1.2 and expected market return is 11%. The required return is:
Correct
CAPM: Ke = Rf + β(Rm − Rf) = 6% + 1.2 × (11% − 6%) = 12%. Beta measures sensitivity to systematic market risk.
Incorrect
CAPM: Ke = Rf + β(Rm − Rf) = 6% + 1.2 × (11% − 6%) = 12%. Beta measures sensitivity to systematic market risk.
Unattempted
CAPM: Ke = Rf + β(Rm − Rf) = 6% + 1.2 × (11% − 6%) = 12%. Beta measures sensitivity to systematic market risk.
-
Question 12 of 20
12. Question
A beta of 0.7 generally indicates that a security:
Correct
Beta measures systematic risk relative to the market. A beta of 0.7 indicates lower market sensitivity than beta 1, but it does not guarantee returns or eliminate company-specific risk.
Incorrect
Beta measures systematic risk relative to the market. A beta of 0.7 indicates lower market sensitivity than beta 1, but it does not guarantee returns or eliminate company-specific risk.
Unattempted
Beta measures systematic risk relative to the market. A beta of 0.7 indicates lower market sensitivity than beta 1, but it does not guarantee returns or eliminate company-specific risk.
-
Question 13 of 20
13. Question
Arbitrage Pricing Theory explains expected returns primarily through:
Correct
APT relates expected returns to sensitivities to multiple systematic factors and associated risk premiums. Unlike basic CAPM, it does not rely on a single market factor.
Incorrect
APT relates expected returns to sensitivities to multiple systematic factors and associated risk premiums. Unlike basic CAPM, it does not rely on a single market factor.
Unattempted
APT relates expected returns to sensitivities to multiple systematic factors and associated risk premiums. Unlike basic CAPM, it does not rely on a single market factor.
-
Question 14 of 20
14. Question
A practical project risk register should generally record:
Correct
A risk register supports structured risk management by documenting risks, their assessment, accountable owners, planned responses and monitoring status.
Incorrect
A risk register supports structured risk management by documenting risks, their assessment, accountable owners, planned responses and monitoring status.
Unattempted
A risk register supports structured risk management by documenting risks, their assessment, accountable owners, planned responses and monitoring status.
-
Question 15 of 20
15. Question
An Indian company expects to receive USD in six months. A depreciation of the dollar against the rupee would generally:
Correct
If the dollar weakens against the rupee, each USD converts into fewer rupees, reducing the INR value of a future dollar receipt. A forward or option hedge may help manage this exposure.
Incorrect
If the dollar weakens against the rupee, each USD converts into fewer rupees, reducing the INR value of a future dollar receipt. A forward or option hedge may help manage this exposure.
Unattempted
If the dollar weakens against the rupee, each USD converts into fewer rupees, reducing the INR value of a future dollar receipt. A forward or option hedge may help manage this exposure.
-
Question 16 of 20
16. Question
Country risk in an overseas investment may include:
Correct
Country risk includes political, sovereign, transfer, convertibility and other country-specific factors that can impair the ability to operate, remit funds or realise expected cash flows.
Incorrect
Country risk includes political, sovereign, transfer, convertibility and other country-specific factors that can impair the ability to operate, remit funds or realise expected cash flows.
Unattempted
Country risk includes political, sovereign, transfer, convertibility and other country-specific factors that can impair the ability to operate, remit funds or realise expected cash flows.
-
Question 17 of 20
17. Question
Transfer pricing can affect an overseas project appraisal because it may:
Correct
Intercompany prices influence where profits and taxable income arise. Appraisal should use compliant transfer-pricing assumptions and focus on consolidated incremental cash flows after relevant taxes and restrictions.
Incorrect
Intercompany prices influence where profits and taxable income arise. Appraisal should use compliant transfer-pricing assumptions and focus on consolidated incremental cash flows after relevant taxes and restrictions.
Unattempted
Intercompany prices influence where profits and taxable income arise. Appraisal should use compliant transfer-pricing assumptions and focus on consolidated incremental cash flows after relevant taxes and restrictions.
-
Question 18 of 20
18. Question
Which action is an example of risk mitigation rather than risk avoidance?
Correct
Mitigation reduces either the likelihood or impact of a risk while the activity continues. Cancelling a project is risk avoidance; accepting risk means proceeding without additional response.
Incorrect
Mitigation reduces either the likelihood or impact of a risk while the activity continues. Cancelling a project is risk avoidance; accepting risk means proceeding without additional response.
Unattempted
Mitigation reduces either the likelihood or impact of a risk while the activity continues. Cancelling a project is risk avoidance; accepting risk means proceeding without additional response.
-
Question 19 of 20
19. Question
Why is expected NPV alone insufficient to describe all aspects of project risk?
Correct
Expected NPV is an average and does not show dispersion, downside probability or tail outcomes. Variance, scenarios, simulation and risk tolerance may also be needed.
Incorrect
Expected NPV is an average and does not show dispersion, downside probability or tail outcomes. Variance, scenarios, simulation and risk tolerance may also be needed.
Unattempted
Expected NPV is an average and does not show dispersion, downside probability or tail outcomes. Variance, scenarios, simulation and risk tolerance may also be needed.
-
Question 20 of 20
20. Question
After sensitivity analysis shows project NPV is most sensitive to sales volume, management should next:
Correct
Sensitivity analysis identifies influential variables. Management should understand their drivers, improve forecasts, consider commercial mitigations and monitor early indicators rather than treating the variable as certain.
Incorrect
Sensitivity analysis identifies influential variables. Management should understand their drivers, improve forecasts, consider commercial mitigations and monitor early indicators rather than treating the variable as certain.
Unattempted
Sensitivity analysis identifies influential variables. Management should understand their drivers, improve forecasts, consider commercial mitigations and monitor early indicators rather than treating the variable as certain.